PROJECT NAME:
The El Campo Grande Project
CLIENT:
Thomas & Mack Development Group
PROJECT SIZE:
38.20 Acres
SERVICES PROVIDED:
Phase I, Phase II
Over the years, CivilWorksInc³ has had the
opportunity to work on several projects for
The Thomas & Mack Development Group.
One such project, El Campo Grande, is comprised of
38.20 acres for commercial development.
The vacant site is bordered by Nellis Air
Force Base to the South and West. In
2003, Thomas & Mack initially requested our
services with a Phase I Environmental Site
Assessment (ESA).
The objective of a Phase I ESA is to to determine the
presence or absence of recognized
environmental conditions, defined by the
American Society For Testing and Materials,
due to past or present uses of the property
or other properties in the vicinity.
The El Campo Grande property is also situated near a
former landfill. As a result, an
on-going Phase II Hydrology
Well-Sampling was requested.
CivilWorksInc, performs
well-testing to monitor the ground water
conditions. |
|